APPLYING FOR NEW SERVICE CONNECTION
-
ABOUT THE SERVICE:
• The connection will not be made until the application is approved and all charges were settled. -
WHO MAY AVAIL THE SERVICE?
• All bonafide residents of Jaen, Nueva Ecija -
SCHEDULE OF AVAILABILITY OF THE SERVICE:
• Monday to Friday
• 8:00 am – 5:00 pm
• No noon break -
WHAT ARE THE REQUIREMENTS?
1.) Accomplished Service Application form
2.) 1 pc. 2×2 picture
3.) Photocopy of valid ID (company ID, drivers license, Postal ID or any valid ID acceptable to JWD)
4.) Brgy. Clearance
5.) Authorization letter from lot /building owner (if applicant is a tenant)* Any other proof of residency acceptable to JWD
Additional requirements for commercial class:
• Photocopy of Business / Mayor’s / DTI permit -
DURATION (under normal circumstances):
• Application within 10 minutes depending on the complexity
• Inspection within 2 working days
• Service Line Tapping 5 – 10 days -
*The Management reserves the right to reject any application if not passed with the required criterion.
*All ID’s should bear signature, picture and exact address.
HOW TO AVAIL THE SERVICE
-
STEP 1
-
CLIENT :
• Present applicant’s copy of inspection slip and fill-out SACO and submit photocopy of valid ID , 1 pc 2×2 picture, Barangay Clearance, Certificate and authorization if necessary -
SERVICE PROVIDER:
• Prepare concessionaire SACO/Contract form and action report.
• Advice the customer to proceed to Cashier for payment of installation cost -
DURATION:
• 15 minutes -
OFFICER IN CHARGE:
• Inspector -
FORM:
• Service Application Construction Order (SACO)
• Inspection Slip -
END OF TRANSACTION
-
STEP 2
-
CLIENT :
• Pay necessary cost of materials, fees and charges indicated in SACO -
SERVICE PROVIDER:
• Accept Payment & issue official receipt
• Forward all documents to Commercial Department for preparation & approval maintenance order & action slip. -
DURATION:
• 10 minutes -
OFFICER IN CHARGE:
• Cashier -
FEES & CHARGES:
• Application Fee: ₱ 150.00
• Service Fee:
– Tabing Linya – ₱ 200.00
– Bagtas – ₱ 300.00
– Boring – ₱ 500.00
– Materials: ₱ 2368.25
Note:
• Cost of Materials varies depending on the location & size of mainline concrete demolition & restoration
• Fees, Charges and cost of materials are subject to increase without prior notice in case of inflation -
Form:
• Official Reciept -
END OF TRANSACTION
-
STEP 3
-
CLIENT :
• Sign Action Report Form upon completion of installation -
SERVICE PROVIDER:
• Installation of Water Service Connection
– Tapping
– Boring -
DURATION:
• 5 working days (Tapping)
• 10 working days (Boring) -
OFFICER IN CHARGE:
• Maintenance /Plumber -
FORM:
• Action Report Form
• Acknowledgement Slip -
END OF TRANSACTION